Project Update - March 26th, 2020 egschooladm egschooladm / Thursday, March 26, 2020 0 2282 Article rating: No rating Please see below project update for the Elbridge Gerry Elementary School: Demolition and removal of the Lower Bell building was completed the week of 3/16/20. Interior Abatement activities for the Upper Bell building completed the week of 3/16/20. Abatement and removal of the Upper Bell roof is in progress and will complete the week of 3/23/20. Selective demolition of the Upper Bell exterior wall systems are in progress and will continue through the week of 4/6/20. Demolition and removal of the Upper Bell foundation systems are scheduled to commence the week of 4/6/20. Balance of the scheduled tree removal to be completed the week of 3/30/20. First round of pre-blast inspection notices have been sent via certified mail on Tuesday 3/24/20. Notices have been sent to property owners within the state required circumferance and all direct abutters to the project site. Mobilization of the Site Enable contractor to commence the week of 4/6/20. Ledge/Rock Profiling activity to commence the week of 4/13/20. Read more
Project Update - March 17th, 2020 egschooladm egschooladm / Tuesday, March 17, 2020 0 2272 Article rating: No rating Please see below project update for the Elbridge Gerry Elementary School: Erosion Control measures have been completed onsite as required. Temporary Pest & Rodent Control measures have been installed onsite. Existing items identified to be salvaged and saved have been transported and delivered to the designaged area within Town. Demolition of the Lower Bell building commenced as scheduled the week of 3/2/20. Demolition is to continue through the week of 3/16/20. Interior Abatement activities for the Upper Bell building are to continue through the week of 3/16/20. Abatement and removal of the Upper Bell roof commenced the week of 3/9/20 and will continue through the week of 3/16/20. Selective demolition of the Upper Bell exterior wall systems are scheduled to commence the week of 3/23/20. Disconnect of the main electrical feed to the Upper Bell building was completed by Marblehead light on 3/9/20. All existing utility poles on site scheduled to removed was completed by Marblehead Light at this time. Read more
Project Update - March 2nd, 2020 egschooladm egschooladm / Monday, March 2, 2020 0 2369 Article rating: No rating Please see below project update for the Elbridge Gerry Elementary School: Construction office trailers arrived onsite week of 2/24/20. Trailer set-up and hook-up of utilities (Electrical, Water and Sewer) are on-going through the weeks of 3/2/20 and 3/9/20. Site Perimeter Construction fence & scrim is complete along Baldwin Road and construction entrances. Perimeter fence inside of the project site is on-going the week of 3/2/20. Erosion Control measures are in-progress and will be on-going the week of 3/2/20. Temporary Pest & Rodent Control measures to be installed the week of 3/2/20. Existing items identified to be salvaged and saved have been collected onsite. Project team will coordinate with the Town of Marblehead for transport and delivery of salvage items to designaged area the week of 3/9/20. Abatement activites for the Lower Bell building was completed week of 2/24/20. Disconnect of the main electrical feed to the Lower Bell building has been completed by Marblehead Light. Demolition of the Lower Bell building is scheduled to commence the week of 3/2/20. Abatement activities for the Upper Bell building are on-going through the weeks of 3/2/20 and 3/9/20. Abatement and removal of the Upper Bell roof is scheduled to commence the week of 3/9/20 Disconnect of the main electrical feed to the Upper Bell building is scheduled for the week of 3/9/20 by Marblehead Light. Read more
Project Update - February 10th, 2020 egschooladm egschooladm / Monday, February 10, 2020 0 2382 Article rating: No rating Please see below project update for the Elbridge Gerry Elementary School: Marblehead Water & Sewer installed temporary hydrant on the property to support temporary water needs for the project. National Grid disconnected the natural gas service lines to the Upper and Lower Bell School buildings the week of 2/3/20. Project team coordinating with National Grid to coordinate and schedule remaining gas main cut & cap in Baldwin Road. Site Perimeter Construction fence & scrim tentatively scheduled to commence week of 2/17/20. Erosion Control measures scheduled to commence week of 2/24/20. Selective site demolition and stone pad area to support CM & OPM Trailers following the completion of construction fence & erosion control measures. Read more
Neighborhood Meeting Presentation - January 13th, 2020 egschooladm egschooladm / Monday, January 20, 2020 0 1 Article rating: No rating Click the Read More link to the right to view the Agenda and Presentation. (Click your browsers BACK button to return to the site) Read more