Lucretia and Joseph Brown Elementary School Project

egschooladm egschooladm
/ Categories: Construction

Saturday Work - 7/24/21

The project will be working on the site this Saturday 7/24/21.  Activities will consist of the following:

  • General Trades will continue drywalling of the Bridge/Boat Hull in the main lobby, continue installing door hardware, and continue drywall and tapping on the stage.   
  • Ceiling contractor will focus on the entry corridor wood slat ceiling.  
  • The Electrical contracotor will continue working on specialty fixture install and fire alarm devicing.  
  • The Telecom contractor will continue working in the main distribution room. 
  • The Painter will be painting the stage and cafeteria. 
  • The flooring contractor will contineu on 2nd level corridors, 1st level breakout rooms, and kitchen epoxy flooring. 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.