Lucretia and Joseph Brown Elementary School Project

egschooladm egschooladm
/ Categories: Construction

Saturday Work - 10/2/2021

The project will be working on the site this Saturday 10/2/2021. Activiteis will consist of the following: 

  • Millwork contractor will be working on punchlist items and clean up.   
  • Painting contractor will be painting stair #3 and working on punchlist items. 
  • Landscape contractor will be installing exterior bollards.
  • Window shade contractor will be installing the shades in the gynasium. 
  • The site contractor will be stripping of street sidewalk crossings. 
  • Waterproofing contractor will be working on punch list items and caulking of exterior sidewalks.
  • The mechanical contractor will be continuing balancing activities. 

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Previous Article Project Update - Week of 9/27/21
Next Article Project Update - Week of October 4th 2021
Print
2387 Rate this article:
No rating

Theme picker