Lucretia and Joseph Brown Elementary School Project

Evening Equipment Departure - May 16, 2020

egschooladm egschooladm 0 2020 Article rating: No rating

The onsite ledge crushing activities are scheduled to be completed Friday 6/12/20.  The contractor will begin demobilizing the equipment Monday 6/15 and preparing it for transport on Tuesday 6/16.  Please see below detailed schedule of activites for these two days:

  • Monday - 6/15/20 
    • Demobilize stacker unit (conveyor equipment), load it for transport and remove from site after 8AM.
    • Begin dismantling ledge crushing equipment during normal work hours.

 

  • Tuesday - 6/16/20
    • Complete dismantle of ledge crushing equipment and prepare it for transport.
    • Transport personnel will be onsite by 3PM to load the equipment for transport.  The transport personnel will wait until dusk; approx 8PM to exit the project.  The equipment will exit the project site via Gate C to West Shore Drive to Route 114.
    • The is evening departure was coordinated and scheduled to mitigate an early morning 3AM-7AM departure.

 

This evening equipment departure has been communicated and coordinated with the Marblehead Police Department.        

Ledge Drilling & Blasting Schedule - Week of 6/1/20

egschooladm egschooladm 0 1998 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 6/1/20.

Monday 6/1/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Tuesday 6/2/20:

  • Drilling activities to continue.

 

Wednesday 6/3/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 6/4/20:

  • Drilling activities to continue.

 

Friday 6/5/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Ledge Drilling & Blasting Schedule - Week of 5/25/20

egschooladm egschooladm 0 1934 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/25/20.

Monday 5/25/20:

  • MEMORIAL DAY - NO WORK

 

Tuesday 5/26/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Wednesday 5/27/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 5/28/20:

  • Drilling activities to continue.

 

Friday 5/29/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Ledge Drilling & Blasting Schedule - Week of 5/18/20

egschooladm egschooladm 0 1931 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/18/20.

Monday 5/18/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Tuesday 5/19/20:

  • Drilling activities to continue.

 

Wednesday 5/20/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 5/21/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Friday 5/22/20:

  • Drilling activities to continue.

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Ledge Drilling & Blasting Schedule - Week of 5/11/20

egschooladm egschooladm 0 1945 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/11/20.

Monday 5/11/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Tuesday 5/12/20:

  • Drilling activities to continue.

 

Wednesday 5/13/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 5/14/20:

  • Drilling activities to continue.

 

Friday 5/15/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

RSS
12

Theme picker